Painting Update
Posted on Sep 1st, 2016

As of September 1, carpenters have finished repairs on 24 buildings (2500 - 2544 and 2570). Power washing has been completed on 23 buildings (2500 - 2544). Painters have finished 14 buildings (2500 - 2526). Carpentry and power washing are being done on 2546. Painting is under way on 2528 and 2530. Find out how you can help the work proceed efficiently: see the May 23 memo.